Install a Level-2 EV charger, Home on Julian St (1100 block), Westwood
Westwood's Morrison Road corridor runs on cars, and this Julian St home's driveway has zero charging; a Level-2 charger is the Energy Petal's transport edge for a household ready to go electric. Standard: Level-2 EV charging installation — NEC Article 625 + local electrical permit, UL-listed EVSE (LBC Energy petal). SDG 7/11. Proof: permit + inspection pass + commissioning photos + GPS Method (Level-2 EV charging installation — NEC Article 625 + local electrical permit, UL-listed EVSE (LBC Energy petal). SDG 7/11.): 1. Run/verify the service load calculation, confirm panel capacity and the conduit path, and photograph the panel schedule and driveway/garage location before work. 2. Install the branch circuit (conduit, conductors, breaker) sized per the EVSE nameplate and NEC 625; torque and log terminations. 3. Mount and wire the listed EVSE at the required height with cable management; label the circuit. 4. Commission: verify voltage, protection function, and a full charge session; register networked units. 5. Pass the electrical inspection and photograph the finished install, breaker and labels. Done when: permit + inspection pass + commissioning photos + GPS
How this work is done
A documented method, so this packet comes out the same whoever does it. Typically 180–480 minutes. Method of record: Level-2 EV charging equipment installation per NEC Article 625 + local electrical permit (ENERGY STAR / UL listed EVSE) — licensed electrician; assess→install→verify
Bring
- UL-listed Level-2 EVSE + mounting hardware
- conductors/conduit, breaker and GFCI protection per NEC 625 plan
- multimeter/clamp meter + torque screwdriver (licensed electrician)
- load calculation worksheet + permit
Steps
- 1. ASSESS: run/verify the service load calculation for the new circuit, confirm panel capacity and the run path, and photograph the panel schedule and install location before work.
- 2. Install the branch circuit (conduit, conductors, breaker) sized per the EVSE nameplate and NEC 625; torque terminations to spec.
- 3. Mount and wire the EVSE at the required height/location (clear of the parking envelope, cable management per listing) and label the circuit.
- 4. Commission: verify voltage, GFCI/CCID function, and a full charge session on a vehicle or tester; register the unit if networked.
- 5. VERIFY: pass the electrical inspection; photograph the completed installation, breaker, and label; record the charge-session proof and leave the owner the operating info.
If it does not match the plan
- Panel lacks capacity per the load calc -> STOP: load-manage (NEC 625.42) or upgrade first; never overload.
- Missing GFCI/CCID protection where required -> not done until corrected.
- Aluminum-to-copper or damaged terminations found -> licensed electrician remediates before energizing.
What counts as done
- Load calculation on file and breaker/conductors match the EVSE nameplate
- Electrical inspection passed; circuit labeled; terminations torqued and logged
- A verified charge session recorded (photo of charging state / session log)
Proof is measured against these, not judged by taste.
Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.