intermediate work · Host-invited home, Superior Avenue area, Glenville, Cleveland, OH 44108

Fit interior storm-window film through an invited Cleveland home

Single-pane windows are standard in Cleveland's century homes, and full replacement is out of reach for most east side households. Interior film kits on every leaky window deliver a real fraction of replacement's benefit for a hundredth of the cost โ€” the right intermediate rung after draft sealing. Standard: DOE storm window and film retrofit guidance; SDG 7 Affordable and Clean Energy. Proof: Before/after photos of every filmed window Method (DOE storm window and film retrofit guidance; SDG 7 Affordable and Clean Energy.): 1. Confirm the host's invitation and measure every single-pane window on the fix list. 2. Clean each frame and apply the double-sided mounting tape. 3. Stretch the film, fix it to the tape, and shrink it drum-tight with a hair dryer. 4. Trim edges cleanly and check each window for gaps. 5. Photograph each filmed window before and after with GPS and date on and record the count. Done when: Before/after photos of every filmed window

Where
Host-invited home, Superior Avenue area, Glenville, Cleveland, OH 44108
Pay
$85 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
Before/after photos of every filmed window

This is exactly what gets it approved. Nothing settles without it.

Level
intermediate
Open until
2026-09-01

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 90โ€“240 minutes. Method of record: Ohio Development Services Agency Home Weatherization Assistance Program (HWAP) โ€” the state pass-through of the DOE Weatherization Assistance Program's cold-climate field protocol: blower-door-directed air sealing toward a CFM50 infiltration target, attic insulation to R-49 / wall cavity to R-13, and mandatory pre/post combustion-safety testing before any tightening closes out.

Bring

Steps

  1. 1. Walk the home with the occupant, note every combustion appliance present, and photograph each nameplate before any work begins.
  2. 2. Set up the calibrated blower door in the main entry and record the baseline CFM50 reading.
  3. 3. Trace and photograph the top infiltration paths with a smoke pencil (rim joist, attic hatch, penetrations, window/door perimeters).
  4. 4. Run the pre-tightening combustion-safety check (ambient CO reading, spillage test at draft hoods) with the blower door off; a failed check stops the job and routes to a licensed HVAC technician before any sealing.
  5. 5. Air-seal the ranked leak paths in order and bring attic insulation to R-49 / accessible wall cavity to R-13 per the HWAP job sheet, maintaining required soffit-to-ridge ventilation.
  6. 6. Re-run the blower-door test to confirm the new CFM50 result.
  7. 7. Run the mandatory post-tightening combustion-safety re-test; a failed re-test stops the job and routes to a licensed HVAC technician for venting correction before further sealing.
  8. 8. Photograph the finished insulation depth and the passed post-tightening combustion-safety check; enter before/after CFM50, materials used, and the combustion-safety result into the proof record; sign.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.