intermediate work · Host play area near Owens Ave & Nellis Blvd, Las Vegas, NV 89110

Raise a shade sail over an East Las Vegas play area

Playgrounds in East Las Vegas stand empty from May to September — equipment too hot to touch, ground too hot to cross. A tensioned shade sail over a host site's play area gives kids back their summer outdoors, the same fix wealthier valley neighborhoods already have. Standard: Municipal playground shade practice; SDG 11 and SDG 3. Proof: Before/after + midday shade photo Method (Municipal playground shade practice; SDG 11 and SDG 3.): 1. Agree sail placement and anchors with the host site and call 811 for post anchors. 2. Set posts in ground anchors or weighted bases, working at or below 8 feet. 3. Attach and tension the UV-rated sail from the ground with turnbuckles. 4. Check tension, clearance, and hardware. 5. Photograph the sail casting midday shade with date and GPS. Done when: Before/after + midday shade photo

Where
Host play area near Owens Ave & Nellis Blvd, Las Vegas, NV 89110
Pay
$400 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
Before/after + midday shade photo

This is exactly what gets it approved. Nothing settles without it.

Level
intermediate
Open until
2026-09-03

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 90–240 minutes. Method of record: Urban heat-island mitigation for civic hard surfaces and pedestrian waiting areas — high-solar-reflectance (cool) coatings on sidewalks/schoolyards/plazas and shade-sail/structure installs at bus stops and gathering points. EPA Heat Island Reduction Program cool-pavement guidance + ASTM E1918 solar-reflectance testing; municipal right-of-way permit where the surface or structure sits in the public way.

Bring

Steps

  1. 1. Photograph the target surface or waiting area as found, including a mid-day surface-temperature reading, and confirm the right-of-way permit and any utility locates before ground disturbance.
  2. 2. Set cones/barricades for a pedestrian-safe work zone; pressure-wash and clear the surface of debris, or confirm the shade-structure footing location clears underground utilities (811 locate) and meets the manufacturer's anchor spec.
  3. 3. Apply the cool-pavement coating system per manufacturer instructions in the specified number of coats and cure time, OR set and anchor the shade structure/sail per its engineering spec, keeping clearances for accessible passage.
  4. 4. Verify: for coatings, confirm even coverage with no missed sections and let the full cure window pass before reopening to traffic; for structures, confirm anchor torque and structural stability by hand-test.
  5. 5. Take a matching-vantage after photo and a same-conditions surface-temperature reading; log the reading delta.
  6. 6. Enter before/after photos, the temperature readings, materials/product used, and the permit reference into the proof record; sign.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.