intermediate work · Public storm drain near Moss Landing Rd, Moss Landing, CA 95039

Install a trash-capture screen on a Moss Landing storm drain

Storm drains near Moss Landing Harbor carry litter and debris straight into the slough and Monterey Bay every time it rains, with nothing to catch it before the outfall. A simple trash-capture screen at the drain inlet stops debris before it reaches the water. Standard: EPA green-stormwater-infrastructure trash-capture practice — SDG 14. Proof: Photo of the installed screen and a flow check Method (EPA green-stormwater-infrastructure trash-capture practice — SDG 14.): 1. Confirm the drain inlet location and screen size needed. 2. Clear existing debris from the inlet. 3. Install the trash-capture screen per its instructions. 4. Check the screen doesn't block normal water flow. 5. Photograph the installed screen with GPS and date. Done when: Photo of the installed screen and a flow check

Where
Public storm drain near Moss Landing Rd, Moss Landing, CA 95039
Pay
$220 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
Photo of the installed screen and a flow check

This is exactly what gets it approved. Nothing settles without it.

Level
intermediate
Open until
2026-09-03

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 30–75 minutes. Method of record: EPA green-infrastructure inspection (bioretention / bioswale / permeable pavement function + maintenance)

Bring

Steps

  1. 1. Locate the GI asset; record GPS; identify the type (rain garden / bioswale / permeable pavement / tree filter).
  2. 2. Photograph the asset, its inlet, and its outlet/overflow.
  3. 3. Check the inlet and outlet for blockage (sediment, trash, mulch) and note whether flow can enter/leave freely.
  4. 4. Check for standing water and estimate whether it drains within the design window (typically <24-48h after rain); probe media if dry.
  5. 5. Assess vegetation/media condition and estimate sediment/trash accumulation depth.
  6. 6. Note erosion, bypass, or structural damage and list the maintenance needed.
  7. 7. Enter asset type, condition, inlet/outlet status, drainage observation, sediment level, maintenance needs, GPS, photos; sign.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.