intermediate work · Halifax Street and Adams Street, Petersburg, VA

Repair the curb ramp at Halifax and Adams Street (2026-07-20)

The curb ramp at this downtown Petersburg corner is cracked and pools water, a daily obstacle for residents using mobility devices to reach the bus stop. Standard: ADA Public Right-of-Way Accessibility Guidelines, curb ramp compliance Proof: Before/after photos of the ramp and a slope check note. Method (ADA Public Right-of-Way Accessibility Guidelines, curb ramp compliance): 1. Inspect the curb ramp at Halifax Street and Adams Street, Petersburg, VA for cracked concrete, ponding, or a missing detectable-warning surface. 2. Clear debris and loose material from the ramp and the landing at the top and bottom. 3. Patch cracked or spalled concrete sections and reset any loose detectable-warning pavers. 4. Check the ramp slope and landing with a level for basic accessibility. 5. Photograph the finished ramp from the street and sidewalk approach. Done when: Before/after photos of the ramp and a slope check note.

Where
Halifax Street and Adams Street, Petersburg, VA
Pay
$420 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
Before/after photos of the ramp and a slope check note.

This is exactly what gets it approved. Nothing settles without it.

Level
intermediate
Open until
2026-08-19

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 240–600 minutes. Method of record: Curb ramp repair/retrofit to ADA + PROWAG R304 (slope, landing, detectable warning surface), under municipal right-of-way permit — trained crew with wet-cut dust controls; assess→repair→verify

Bring

Steps

  1. 1. ASSESS: measure the existing ramp against PROWAG R304 (running slope ≤8.3%, cross-slope ≤2%, landing, flush transition, detectable warning) and photograph each failure; confirm permit + utility locates before cutting.
  2. 2. Set up cones/barricades and a safe pedestrian detour outside the work zone.
  3. 3. Remove the failed ramp section with wet-cut dust controls; form and place the corrected ramp geometry per the city standard drawing.
  4. 4. Set the detectable warning surface (truncated domes) aligned and embedded per spec; finish transitions flush with the gutter.
  5. 5. VERIFY: re-measure every R304 dimension with the smart level, photograph readings + before/after from matching vantage, water-test the gutter flow line, and close out the permit.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.