intermediate work · Main St at Cherry St, Pine Bluff, AR
Rebuild the broken curb ramp at Main Street and Cherry Street (2026-07-20)
The curb ramp at Main Street and Cherry Street has crumbled to a jagged lip that catches wheelchairs and walkers on a crossing residents use to reach downtown. Rebuilding it restores a level path. Standard: ADA curb ramp standard, accessible public crossing Proof: Photo of the finished ramp with slope measurement logged Method (ADA curb ramp standard, accessible public crossing): 1. Mark the ramp footprint and confirm the required slope 2. Break out the damaged ramp surface 3. Form and pour a new ramp section to ADA slope 4. Cure the surface and add detectable warning texture 5. Photograph the finished ramp with slope logged Done when: Photo of the finished ramp with slope measurement logged
How this work is done
A documented method, so this packet comes out the same whoever does it. Typically 240–600 minutes. Method of record: Curb ramp repair/retrofit to ADA + PROWAG R304 (slope, landing, detectable warning surface), under municipal right-of-way permit — trained crew with wet-cut dust controls; assess→repair→verify
Bring
- right-of-way permit + cones/barricades + pedestrian detour signage
- smart level / digital inclinometer + tape measure
- concrete tools + detectable warning surface (truncated dome) panel per city standard
- wet-cut saw with water feed (dust control)
Steps
- 1. ASSESS: measure the existing ramp against PROWAG R304 (running slope ≤8.3%, cross-slope ≤2%, landing, flush transition, detectable warning) and photograph each failure; confirm permit + utility locates before cutting.
- 2. Set up cones/barricades and a safe pedestrian detour outside the work zone.
- 3. Remove the failed ramp section with wet-cut dust controls; form and place the corrected ramp geometry per the city standard drawing.
- 4. Set the detectable warning surface (truncated domes) aligned and embedded per spec; finish transitions flush with the gutter.
- 5. VERIFY: re-measure every R304 dimension with the smart level, photograph readings + before/after from matching vantage, water-test the gutter flow line, and close out the permit.
If it does not match the plan
- No permit or no utility locate -> STOP: do not cut.
- Cutting without water-fed dust control -> STOP (respirable silica).
- Geometry cannot meet R304 within the existing footprint -> document and route to the city's ADA transition-plan engineer instead of pouring a non-compliant ramp.
What counts as done
- Measured running slope ≤8.3% and cross-slope ≤2% with level photos
- Detectable warning surface installed per standard (alignment + embed photos)
- Flush gutter transition verified (no lip >1/4 inch; water flows along the gutter line)
- Before/after photos + permit close-out reference
Proof is measured against these, not judged by taste.
Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.
Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.