intermediate work · Calle Barbosa, San Juan, PR

Repair a ponding-prone permeable sidewalk section near the canal in Barrio Obrero (2026-07-20)

A sidewalk section near the canal in Barrio Obrero cracks and ponds water after every heavy rain, a real trip hazard on a route people walk daily. A permeable repair fixes the surface and lets stormwater soak in instead of pooling. Standard: LBC Equity petal, public right-of-way access safety Proof: Photos show a repaired, level, draining sidewalk section Method (LBC Equity petal, public right-of-way access safety): 1. Photograph and measure the damaged sidewalk section 2. Clear loose debris and old cracked material 3. Prepare and pour permeable repair material to the correct depth 4. Grade the surface for a smooth, level transition 5. Confirm the repaired section drains without pooling after a test water pour Done when: Photos show a repaired, level, draining sidewalk section

Where
Calle Barbosa, San Juan, PR
Pay
$300 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
Photos show a repaired, level, draining sidewalk section

This is exactly what gets it approved. Nothing settles without it.

Level
intermediate
Open until
2026-08-19

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 240–600 minutes. Method of record: Sidewalk panel repair with permeable finish per ADA/PROWAG surface requirements + EPA permeable pavement BMP, under municipal right-of-way permit — trained crew with wet-cut dust controls; assess→repair→verify

Bring

Steps

  1. 1. ASSESS: measure and photograph each displaced/cracked panel (lift height, cross-slope, ponding), mark the repair extent, and confirm the right-of-way permit and utility locates (811) before any cutting.
  2. 2. Set up cones/barricades and a safe pedestrian detour; keep all work out of the traffic lane.
  3. 3. Remove or wet-cut the failed section with water-fed dust controls; excavate to the design subbase and correct the root or subgrade cause (root-prune only per the city arborist standard).
  4. 4. Place open-graded base and the permeable surface (pavers or pervious mix) to ADA/PROWAG slope and lippage limits; compact and edge.
  5. 5. VERIFY: check cross-slope ≤2% and vertical discontinuity ≤1/4 inch, water-test infiltration, photograph before/after from the same vantage, and close out the permit.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.