advanced work · Mobile-crane lift site, Tampa FL
Crane & rigging pre-lift spotter survey — mobile crane, Tampa (2026-07-21)
A mobile crane lift in Tampa is set up without documented ground/outrigger, clearance, or rigging condition checks. Standard: OSHA 29 CFR 1926 Subpart CC — Cranes & Derricks in Construction (§§1926.1400–1442) Proof: photo from a safe distance per checklist section + GPS + Subpart CC checklist + power-line/outrigger/swing-zone/rigging status + tiered findings routed to the lift director Method (OSHA 29 CFR 1926 Subpart CC (Cranes & Derricks in Construction, §§1926.1400–1442) pre-lift spotter survey — safe-distance observation of setup, clearances, and rigging; documentation only, ~45-90 min): 1. Check in with the lift director / crane operator; confirm scope, don PPE, and confirm you observe-and-document from a safe distance only — you never rig, signal, level, or direct the lift (Subpart CC reserves these for the qualified rigger / signal person / operator). 2. Ground & setup: photograph and document firm/drained/level ground, full outrigger/stabilizer extension with pads/cribbing, and the crane's level indication (§§1926.1402/.1404). 3. Power-line clearance: identify overhead lines and confirm the planned swing/boom keeps the Table A minimum approach distance (default 20 ft for lines ≤350 kV) or that a documented de-energize / encroachment-prevention plan is in place (§1926.1408). 4. Swing radius / crush zone: confirm the area swept by the rotating superstructure (counterweight) is barricaded to keep workers out (§1926.1424). 5. Personnel & rigging: confirm a qualified signal person + an agreed signal method, a qualified rigger, the load chart / rated capacity posted, and slings/shackles/hooks (with safety latches) in serviceable condition per the rigger's inspection (§§1926.1419/.1425/.1428). 6. For each finding, mark the condition against the Subpart CC checklist item, assign a tier (stop-work / correct-before-proceed / monitor), and name the responsible lift director / qualified operator. 7. Enter photos, GPS/address, the checklist, and the tiered findings; sign. Route stop-work items to the lift director / operator with a timestamp — never direct or signal the lift. Equipment: hard hat + safety glasses + hi-vis vest (site PPE), tablet/clipboard with the OSHA Subpart CC pre-lift checklist, camera with zoom (observe from a safe distance), tape measure / measuring wheel (setback and barricade distances from the ground), the crane's load chart / lift plan for reference, flashlight Done when: Ground/outrigger setup (firm/level, full extension, pads/cribbing) photographed and documented; Power-line minimum-approach clearance and swing-radius/crush-zone barricading confirmed and photographed; Qualified signal person + qualified rigger + posted load chart + serviceable rigging (safety latches) documented; Every finding tiered with the lift director / qualified operator named; stop-work items routed with a timestamp
How this work is done
A documented method, so this packet comes out the same whoever does it. Typically 45–90 minutes. Method of record: OSHA 29 CFR 1926 Subpart CC (Cranes & Derricks in Construction, §§1926.1400–1442) pre-lift spotter survey — safe-distance observation of setup, clearances, and rigging; documentation only
Bring
- hard hat + safety glasses + hi-vis vest (site PPE)
- tablet/clipboard with the OSHA Subpart CC pre-lift checklist
- camera with zoom (observe from a safe distance)
- tape measure / measuring wheel (setback and barricade distances from the ground)
- the crane's load chart / lift plan for reference
- flashlight
Steps
- 1. Check in with the lift director / crane operator; confirm scope, don PPE, and confirm you observe-and-document from a safe distance only — you never rig, signal, level, or direct the lift (Subpart CC reserves these for the qualified rigger / signal person / operator).
- 2. Ground & setup: photograph and document firm/drained/level ground, full outrigger/stabilizer extension with pads/cribbing, and the crane's level indication (§§1926.1402/.1404).
- 3. Power-line clearance: identify overhead lines and confirm the planned swing/boom keeps the Table A minimum approach distance (default 20 ft for lines ≤350 kV) or that a documented de-energize / encroachment-prevention plan is in place (§1926.1408).
- 4. Swing radius / crush zone: confirm the area swept by the rotating superstructure (counterweight) is barricaded to keep workers out (§1926.1424).
- 5. Personnel & rigging: confirm a qualified signal person + an agreed signal method, a qualified rigger, the load chart / rated capacity posted, and slings/shackles/hooks (with safety latches) in serviceable condition per the rigger's inspection (§§1926.1419/.1425/.1428).
- 6. For each finding, mark the condition against the Subpart CC checklist item, assign a tier (stop-work / correct-before-proceed / monitor), and name the responsible lift director / qualified operator.
- 7. Enter photos, GPS/address, the checklist, and the tiered findings; sign. Route stop-work items to the lift director / operator with a timestamp — never direct or signal the lift.
If it does not match the plan
- Planned swing/boom within the Table A minimum approach distance of an energized line (default <20 ft for lines ≤350 kV) with no de-energize/encroachment plan -> STOP-WORK: document, keep clear, route to the lift director; never direct the lift.
- Outriggers/stabilizers not fully extended or on inadequate ground/cribbing, or a non-level crane -> STOP-WORK for the lift; route to the qualified operator; never operate or level it yourself.
- Swing/crush zone not barricaded, no qualified signal person, or damaged rigging (no safety latch, cut/kinked sling) -> STOP-WORK; keep workers clear; route to the lift director / qualified rigger.
- Any rigging, signaling, leveling, or lift direction -> observe-and-document only; the qualified rigger / signal person / operator performs and approves these. Approval and correction stay human.
What counts as done
- Ground/outrigger setup (firm/level, full extension, pads/cribbing) photographed and documented
- Power-line minimum-approach clearance and swing-radius/crush-zone barricading confirmed and photographed
- Qualified signal person + qualified rigger + posted load chart + serviceable rigging (safety latches) documented
- Every finding tiered with the lift director / qualified operator named; stop-work items routed with a timestamp
Proof is measured against these, not judged by taste.
Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.