advanced work · the public streets and curb ramps around El Campo City Hall, 315 E Jackson St, El Campo, TX 77437
Retrofit missing detectable warning domes onto a curb ramp, ramp 1, the public streets and curb ramps around El Campo City Hall, 315 E Jackson St, El Campo, TX 77437
Fund it for $310. Proof lands onchain when it's done.
A pedestrian curb ramp near El Campo City Hall has no detectable warning surface, leaving a blind or low-vision pedestrian no tactile cue for the street edge.
How this work is done
A documented method, so this packet comes out the same whoever does it. Typically 240–600 minutes. Method of record: Curb ramp repair/retrofit to ADA + PROWAG R304 (slope, landing, detectable warning surface), under municipal right-of-way permit, trained crew with wet-cut dust controls; assess→repair→verify
Bring
- right-of-way permit + cones/barricades + pedestrian detour signage
- smart level / digital inclinometer + tape measure
- concrete tools + detectable warning surface (truncated dome) panel per city standard
- wet-cut saw with water feed (dust control)
Steps
- 1. ASSESS: measure the existing ramp against PROWAG R304 (running slope ≤8.3%, cross-slope ≤2%, landing, flush transition, detectable warning) and photograph each failure; confirm permit + utility locates before cutting.
- 2. Set up cones/barricades and a safe pedestrian detour outside the work zone.
- 3. Remove the failed ramp section with wet-cut dust controls; form and place the corrected ramp geometry per the city standard drawing.
- 4. Set the detectable warning surface (truncated domes) aligned and embedded per spec; finish transitions flush with the gutter.
- 5. VERIFY: re-measure every R304 dimension with the smart level, photograph readings + before/after from matching vantage, water-test the gutter flow line, and close out the permit.
If it does not match the plan
- No permit or no utility locate -> STOP: do not cut.
- Cutting without water-fed dust control -> STOP (respirable silica).
- Geometry cannot meet R304 within the existing footprint -> document and route to the city's ADA transition-plan engineer instead of pouring a non-compliant ramp.
What counts as done
- Before photo of the ramp with no detectable warning surface
- Dome spacing measurement confirming PROWAG R304 compliance
- Anchor torque or adhesive cure confirmation
- After photo of the installed detectable warning panel
Proof is measured against these, not judged by taste.
Funding this work is a purchase or a vote, same act: you either want this done here, or you want the world to contain it. A vote is free and signed; funding starts at one cent and anything beyond the wage is recorded as a premium for the worker. Either way the money settles only on accepted proof. An agent can fund it in one x402 call: POST /nurture/fund {"workId":"WORK_1785929720799_elx3aly","funderWallet":"0xYOU"}.
Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.
Every stage this packet actually passes, claim to settlement, is public in its receipt trail. A stage that has not happened is not claimed.
Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.