Anyone can start here · Storm drains near 12th Ave S & 3rd St S, Nampa, ID 83651

Stencil 'drains to Indian Creek' markers on Nampa's storm drains

Nampa's street drains feed the Indian Creek system, but on these fast-growing blocks most people assume street water gets treated. Oil, soap, and lawn chemicals go straight to the creek. A painted curb marker at each drain is the cheapest permanent education there is. Standard: City of Nampa stormwater education program (drain marking); SDG 6 (Clean Water and Sanitation). Proof: photo of each stenciled drain plus the route log Method (City of Nampa stormwater education program (drain marking); SDG 6 (Clean Water and Sanitation).): 1. Confirm the marking route and stencil kit with the city stormwater program. 2. Sweep and dry the curb face at each drain. 3. Apply the stencil with approved curb paint. 4. Log each marked drain's corner on the route sheet. 5. Photograph each finished stencil, GPS-tagged and dated. Done when: photo of each stenciled drain plus the route log

Where
Storm drains near 12th Ave S & 3rd St S, Nampa, ID 83651
Pay
$160 proposed

This packet is not funded yet, so this figure is a proposed price and not money waiting in escrow. If a buyer funds it, approved proof settles that price onchain. If nobody funds it, approved proof earns provable credit toward the work instead of cash. You see which before you claim, never after.

Proof
photo of each stenciled drain plus the route log

This is exactly what gets it approved. Nothing settles without it.

Level
entry
Open until
2026-09-18

How this work is done

A documented method, so this packet comes out the same whoever does it. Typically 30–75 minutes. Method of record: EPA green-infrastructure inspection (bioretention / bioswale / permeable pavement function + maintenance)

Bring

Steps

  1. 1. Locate the GI asset; record GPS; identify the type (rain garden / bioswale / permeable pavement / tree filter).
  2. 2. Photograph the asset, its inlet, and its outlet/overflow.
  3. 3. Check the inlet and outlet for blockage (sediment, trash, mulch) and note whether flow can enter/leave freely.
  4. 4. Check for standing water and estimate whether it drains within the design window (typically <24-48h after rain); probe media if dry.
  5. 5. Assess vegetation/media condition and estimate sediment/trash accumulation depth.
  6. 6. Note erosion, bypass, or structural damage and list the maintenance needed.
  7. 7. Enter asset type, condition, inlet/outlet status, drainage observation, sediment level, maintenance needs, GPS, photos; sign.

If it does not match the plan

What counts as done

Proof is measured against these, not judged by taste.

Claim it on the board

Claiming is free. You sign to prove the wallet is yours, and signing costs nothing: no card, no deposit, no fee. An agent can claim this for you with one call to POST /labor/claim, documented at /llms.txt.

Posted pay is not paid pay: settlement follows accepted proof, never the other way around. Vealth does not employ or vet workers, and claiming is not a promise of payment. See how proof and receipts work.